1. Yes, it's a whole new look! Have questions or need help? Please post your question in the New Forum Questions thread Click the X to the right to dismiss this notice
    Dismiss Notice
  2. Seeing tons of unread posts after the upgrade? See this thread for help. Click the X to the right to dismiss this notice
    Dismiss Notice

Asphalt Project

Discussion in 'Broadlands Community Issues' started by The Broadlands Community, Sep 1, 2021.

  1. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    Broadlands Association has contracted with Finley Asphalt & Concrete to repave streets on Bankbarn Terrace and in the Village Dr. and Overland Park sections this Fall. A portion of this project includes concrete and trail work.

    Concrete work will commence on September 7th, with trail work starting the following week and then asphalt repaving beginning September 20th, all weather permitting. Please refer to our website for the MAPS & SCHEDULE as your cooperation will be needed to relocate your cars since parking or driving on the road will be prohibited during construction hours. During concrete work, please avoid parking within 30 feet of any areas marked with an "X".

    Please note: Mail deliveries may be affected. The HOA will try to coordinate with Patriot Disposal to pick up trash/recycling prior to work starting on Mondays/Thursdays. Prior to the commencement of this project, details will be posted on our website and a notice will be distributed by the contractor and placed on your door.
     
  2. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    Concrete Apron Repairs begin Tuesday, September 7th!!

    These driveways will be closed for 36 hours beginning at 7:30am through the next day at 6:00pm to allow time to cure. Please remove cars from driveways or garages if you are going to need to use them while your apron is being repaired, otherwise they will not be assessible for 36 hours:

    • Tuesday Sept. 7th:
      • 21909 Larchmont Way (driveway curb)
    • Wednesday Sept. 8th:
      • 21931 Windover Drive (Driveway Curb
      • 21926 Windover Drive (Driveway Curb)
      • 21910 Windover Drive (Driveway Curb)
      • 21902 Windover Drive (Driveway Apron & Curb)
    • Thursday Sept. 9th:
      • 21882 + 21874 + 21878 Windover Drive (Driveway Apron & Curb)
      • 21890 Windover Drive (Driveway Curb)
      • 21866 Windover Drive (Driveway Curb)
      • 21854 + 21858 Windover Drive (Driveway Curb)
    • Friday Sept. 10th:
      • 21550 + 21568 + 21586 + 21588 Bankbarn Ter. (Driveway Apron & Curb)

    IF YOUR ADDRESS IS NOT LISTED ABOVE, YOU ARE NOT AFFECTED BY THE CONCRETE REPAIRS HAPPENING AROUND THE COMMUNITY. THE MAP MAY LIST YOUR STREET, HOWEVER, THAT DOES NOT MEAN YOUR DRIVEWAY WILL BE AFFECTED. ONLY THE ADDRESSES ABOVE WILL HAVE THEIR CURB AFFECTED BY CONCRETE REPAIRS AND WILL NOT HAVE ACCESS TO THEIR DRIVEWAY DURING THE 36 HOURS OF CONSTRUCTION.
     
    Last edited: Sep 7, 2021
  3. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    Fall Asphalt Project: Phase 1 of Road work Begins September 20th
    Only roads in the Village Dr area, Bankbarn Ter, & Overland Park section are affected during this fall project. Please refer to our website here, Fall Asphalt Project Information, for all details and updates. This work will require the cooperation of all residents since parking or driving on the road will be prohibited during construction hours.
     
  4. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    Fall Asphalt Project: Phase 2 of Road work Begins September 27th

    What: Asphalt Road Repairs Read Notice
    When: Monday Sept. 27 through Friday Oct. 1, 7:30am-6:30pm daily
    Where: Phase 2 (ORANGE) Map:
    • Milford Drive (EAST) – PARTIAL (from Windover Drive to intersection)
    • Windover Drive (NORTH) – PARTIAL (From Milford Drive (EAST) to Larchmont Way
     
  5. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    Fall Asphalt Project: Phase 3 of Road Work Begins October 4th:

    What: Asphalt Road Repairs Read Notice
    When: Monday, Oct. 4 thru Friday, Oct. 8, 7:30am-6:30pm daily. (This work is weather dependent and may be delayed due to the rainy forecast. Updates will be posted on our website.)
    Where: Map - Phase 3 (PINK) area includes:
    • Windover Drive (SOUTH) – PARTIAL (from Village Drive to Larchmont Way)
    • Larchmont Way (from Village Drive to Windover Drive)
    • Broxton Terrace
     
  6. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    NEXT UP!
    What: Asphalt Road Repairs Read Notice
    When: Monday, Oct. 11 thru Friday, Oct. 15, 7:30am-6:30pm daily.
    Where: Map - Phase 4 (BLUE) area includes:

    • Arbor Greene Way
    • Bayard Terrace
    • Sunderleigh Square
    • Bramblebush Terrace
     
  7. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
  8. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    NEXT UP!
    What: Asphalt Road Repairs Read Notice
    When: Monday, Oct. 25 thru Friday, Oct. 29, 7:30am-6:30pm daily
    Where: Map - Phase 6 (GREEN) area includes:
    • Overland Park (NORTH) – PARTIAL (from Broadlands Blvd to Humbolt Square)
    • Atherton Street – PARTIAL (from Humbolt Square to Overland Park (NORTH))
    • Humbolt Square
     
  9. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    We apologize for the inconvenience, but we learned from the contractor that Phase 6 paving will be delayed by a day. So there will be no road closures today, Monday, October 25th for the following areas:
    • Overland Park (NORTH) – PARTIAL (from Broadlands Blvd to Humbolt Square)
    • Atherton Street – PARTIAL (from Humbolt Square to Overland Park (NORTH))
    • Humbolt Square
    Milling will begin tomorrow morning (10/26), so please be sure to have vehicles relocated off the streets/parking areas or if you wish to access your vehicles.
     
  10. The Broadlands Community

    The Broadlands Community Well-Known Member

    Joined:
    May 13, 2014
    Messages:
    928
    Likes Received:
    83
    Final phase: Nov 1 – Nov 5 (Area 3), 7:30am – 6:30pm daily: Overland Park Map – Phases 7 Schedule
    • Atherton Street – PARTIAL (from Overland Park NORTH to Columbus Street)
    • Claybrooke Circle
    • Columbus Street
    • Center Point Circle
     

Share This Page