Asphalt Repaving Sep 20-Nov 5, 2021

asphalt project

Phase 1 begins September 20th, please click the following blue box to read the important notice that outlines the details of this project:

This project will only affect roads in the Village Dr area, Bankbarn Ter, & the Overland Park section. These roads will be closed from 7:30am-6:30pm each day while under construction, however, you may drive on the road between 6:30pm and 7:30am. Please refer to the maps and schedule below to see list of roads and when work will occur. Your cooperation will be needed to relocate your cars since parking or driving on the road will be prohibited during construction hours


Overview of Maps & Schedules:

Please remember that this schedule is weather dependent and may be delayed. Please check back frequently for updates or be sure you are signed up for the Broadlands Blast by entering your email on our website where you see the Blast logo.

September Calendar>>

NEXT UP! Phase 2 (ORANGE) Map, Monday Sept. 27 through Friday Oct. 1, 7:30am-6:30pm daily

  • Milford Drive (EAST) – PARTIAL (from Windover Drive to intersection)
  • Windover Drive (NORTH) – PARTIAL (From Milford Drive (EAST) to Larchmont Way